Natural Gas Blows Budget for Biomass Project in Ashland
Daily Reporter (Milwaukee) › May 13, 2010
Linked as:
Daily Reporter (Milwaukee) › May 13, 2010
Linked as:Summary
The label of renewable energy will cost Xcel Energy an extra $21.4 million after the utility realized its proposed biomass plant in Ashland will burn too much natural gas.
The Public Service Commission of Wisconsin approved the Bay Front Power Plant project, which will convert the plant's last coal-fired boiler to burn biomass, in December. But the cost increase will push the project back before the PSC for another review.See the full content of this document
Extract
Natural Gas Blows Budget for Biomass Project in Ashland
"We're still as committed to the project as we were before," said David Donovan, Xcel's manager of regulatory policy. "But now we have to figure...
See the full content of this document
Sponsored links
ver las páginas en versión mobile | web
ver las páginas en versión mobile | web
© Copyright 2012, vLex. All Rights Reserved.
Contents in vLex United States
Explore vLex
For Professionals
For Partners
Company
Other documents:
The Weather Man; Lows in the 40s | Global Warming and the Case for Nuclear Energy | latino power | Local Biotech Company Seeks Capital | Sentencia nº 1667 de Consiglio di Stato March 28 2008 | sentencia nº 505 de consiglio di stato, january 29, 2008 | Sentencia nº 1612 de Consiglio di Stato March 28 2008 | sentencia nº 3736 de consiglio di stato july 16 2008